Hales Mill Road Reconstruction Project Phase II

The City Council identified the reconstruction of Hales Mill Road Phase II (Springreen Drive to Asbury Road) in the City's Five Year Capital Plan for reconstruction in the spring of 2023.  A public information meeting was held with a project overview to inform residents of the scope and design of the roadway.  Click here for the roadway presentation.

At the February 28, 2023 City Council meeting, this project was awarded to Eastern Iowa Excavating and Concrete in the amount of $2,562,557.27.   This project consists of utility upgrades and roadway pavement replacement of Hales  Mill Road between Brick Mason Lane and Asbury Road.  The utility improvements include replacement of the sanitary sewer system, and replacement of the storm sewer system.  Construction is slated to begin in Spring of this year and it planned to be completed in the fall of 2023.